Village projects

Works on the ground, with their paperwork attached.

Gaon ke kaam — poora kaagaz ke saath

No work above one lakh is awarded on fewer than three written quotations, opened before the committee. The comparison sheet is published here — including the quotations that lost, and why.

Already built

What eleven years has built.

Ab tak kya bana

The record of works finished or still running since 2015. Costs are the office's own approximations until the audited statements are in.

Water Supply Works

Ongoing

Paani ka kaam

Multiple storage tanks at mountain level, pipelines down to the village, borewells, and the reconstruction and safeguarding of tanks already standing. The single largest head of development spending.

₹20,00,000
Approximate · pending audit
2016 – present

Community Building — Repair & Maintenance

Ongoing

Imarat ki marammat

Structural repair, plastering, boundary walls and ongoing maintenance of the village's community structure.

₹27,50,000
Approximate · pending audit
2017 – present

Village Road Works

Sadak ka kaam

Internal village roads and the approach stretches, laid and repaired in phases.

₹22,50,000
Approximate · pending audit
2018 – 2024

Electrical Street Lighting

Ongoing

Street light

Street lights along the village lanes and the approach road, put up and maintained by the Society.

Cost carried across several years
2019 – present

Boundary Walls

Ongoing

Compound wall

Boundary walls at several village sites, including the burial ground on the north and west faces.

Cost carried across several years
2020 – present

Wells — Reviving & Cleaning

Ongoing

Kuan safai

Reviving old wells that had gone out of use, and periodic cleaning of those still drawn from.

Cost carried across several years
2017 – present

Village Upkeep

Ongoing

Gaon ki safai

Grass clearing, walkway upkeep and general cleaning through the year — the unglamorous work that keeps the village usable in the monsoon.

Cost carried across several years
2015 – present
Running now

Current works and their quotations.

Abhi ke kaam

Each one with its budget, its milestones, and every quotation received — including the ones that lost.

IN PROGRESSStarted 20 May 2026 · target 28 Feb 2027

Village Drinking Water Scheme — Phase 3

गाव पिण्याचे पाणी योजना

A further 20,000-litre tank at mountain level, one new borewell behind the school, and a gravity distribution line covering Madhli Aali, Bazarpeth and Naka. Land cleared by Gram Panchayat resolution dated 12 May 2026.

Milestones
  1. Site survey & water table test24 May 2026
  2. Borewell drilled to 210 ft30 Jun 2026
  3. Tank foundation cast16 Aug 2026
  4. Tank erected at mountain level15 Oct 2026
  5. Distribution line laid20 Dec 2026
  6. Handover to Gram Panchayat28 Feb 2027
Budget & spend
₹18,50,000
₹7,42,000 spent to date
40% funded
Quotations

3 received and opened before the committee.

VendorPlaceAmountReceivedDocumentCommittee noteSelected
Sahyadri BorewellsChiplun₹17,95,0004 May 2026sahyadri-borewells-quote.pdfLowest of three. Agreed to stage payment against milestones.Awarded
Konkan Aqua WorksRatnagiri₹19,12,0006 May 2026konkan-aqua-quote.pdf
Vishwas Drilling & PipesGuhagar₹20,40,0007 May 2026vishwas-drilling-quote.pdfIncludes 2-year AMC; committee felt AMC could be tendered separately.
TENDERINGStarted 1 Jul 2026 · target 31 Jan 2027

Community Building — Roof & Structural Repair

New profiled sheeting on treated rafters over the upper hall, re-plastering of the arcade band and the pierced screens, and repainting in the original ochre and cream.

Milestones
  1. Condition survey by engineer14 Jul 2026
  2. Scaffolding erected20 Aug 2026
  3. Quotations opened8 Sep 2026
  4. Vendor selected
  5. Sheeting replaced
  6. Plaster & paint complete
Budget & spend
₹9,40,000
₹1,68,000 spent to date
18% funded
Quotations

3 received and opened before the committee.

VendorPlaceAmountReceivedDocumentCommittee noteSelected
Rajapur Roofing Co.Rajapur₹9,05,0002 Aug 2026rajapur-roofing-quote.pdf
M. A. Mestry & SonsGuhagar₹9,28,0009 Aug 2026ma-mestry-quote.pdfLocal firm. Did the compound wall in 2019 to satisfaction.
Deccan FabricatorsChiplun₹10,10,00021 Aug 2026deccan-fabricators-quote.pdf
PLANNEDStarted 11 Jun 2026 · target 30 Jun 2027

Village School — Classroom & Toilet Block

Two classrooms and a four-unit girls' toilet block, with a water connection taken from the new village scheme.

Milestones
  1. School committee approval28 Jun 2026
  2. Plan drawn & measured10 Aug 2026
  3. Third quotation awaited
  4. Foundation
Budget & spend
₹14,20,000
₹0 spent to date
0% funded
Quotations

1 received. The committee will not open a comparison until three are in hand.

VendorPlaceAmountReceivedDocumentCommittee noteSelected
Guhagar ConstructionGuhagar₹13,85,00025 Aug 2026guhagar-construction-quote.pdf
COMPLETEDStarted 2 Dec 2025 · target 30 Apr 2026

Burial Ground Boundary Wall

340 running feet of laterite block wall on the north and west sides, with a steel gate matching the compound.

Milestones
  1. Boundary re-measured with Talathi10 Dec 2025
  2. North face built14 Feb 2026
  3. West face rebuilt28 Mar 2026
  4. Gate fitted & accounts closed22 Apr 2026
Budget & spend
₹4,60,000
₹4,47,200 spent to date
97% funded
Quotations

3 received and opened before the committee.

VendorPlaceAmountReceivedDocumentCommittee noteSelected
M. A. Mestry & SonsGuhagar₹4,52,00018 Nov 2025ma-mestry-boundary.pdfAwarded
Palshet LateritePalshet₹4,68,00020 Nov 2025palshet-laterite.pdf
Deccan FabricatorsChiplun₹5,11,00022 Nov 2025deccan-boundary.pdf
PLANNEDStarted 20 Aug 2026 · target 31 Mar 2027

Solar Street Lights — Pewe to Guhagar Road

Eighteen solar street lights along the 2.4 km stretch between the village and the Guhagar road junction, unlit since the line was cut in 2024.

Milestones
  1. Pole positions marked
  2. Quotations invited
Budget & spend
₹6,30,000
₹0 spent to date
0% funded
Quotations

None received yet. The work has not gone out to quotation.

PLANNEDStarted 28 Aug 2026

Patient Transport Vehicle

A shared vehicle for the Ratnagiri and Chiplun hospital runs, presently arranged privately at high cost by each family.

Milestones
  1. Usage survey among households
  2. Running-cost model to committee
Budget & spend
₹11,50,000
₹0 spent to date
0% funded
Quotations

None received yet. The work has not gone out to quotation.